Shared on Behalf of The Broads Authority:


We are delighted to have received funding from the Greater Norwich Growth Board for Wherryman’s Way improvements, working with our partner, Norfolk County Council.


Of a total programme value of £445,148, £216,500 was allocated to fund key access assets, such as replacement bridges on the path alongside Hardley Flood.


Preliminary works completed to date includes, resurfacing along the section that skirts around Rockland Broad to create an ‘access for all’ path; placing dredged sediment to build up the riverbank at Hardley Flood; and new signage installed throughout the route between Norwich and Great Yarmouth.


The remaining phases of work includes:


  • Riverbank      stabilisation and repairs between Bramerton and Surlingham (starting summer 2023)

  • Levelling the riverbank path at Hardley Flood (spring 2023)

  • Footbridge installation at Hardley Flood (starting summer 2023)

  • Repairs to Hardley bird hide

Once these works are all complete, the Wherryman’s Way route will be able to run alongside the river again in these popular walking locations.


For more information and to sign up for Broads Authority Updates go to:

https://www.broads-authority.gov.uk/news/monthly-newsletter


Wherryman's Way improvement progress
Loddon Logo

01508 522 020

EMERGENCY PHONE: 01508 486 128

9am - 12pm Tuesday

9am - 12pm Wednesday

9am - 12pm Thursday

clerk@loddontowncouncil.gov.uk

The Old School, Church Plain 

Loddon, Norfolk, NR14 6EX 

Follow us on Facebook for regular updates.

  • Facebook Link

JOIN OUR MAILING LIST

Thanks - we'll send you a verification email. Click on the link in that email to confirm your address and we'll add you to our mailing list. You can ask to be removed at any time in the future by contacting the clerk.

Thanks to Carl Davidson for the website photography

bottom of page