A146 Loddon Bypass, Loddon – Bus Stop Improvements and Drainage Maintenance
26 June 2025
Sharing on behalf of Norfolk County Council:
A146 Loddon Bypass, Loddon – Bus Stop Improvements and Drainage Maintenance
Bus stop improvement work and essential drainage maintenance work along the A146 Loddon Bypass, Loddon, is due to start on Monday 7 July 2025.
The work will involve constructing new sections of footway, installing two new bus stops, and repairing a section of existing highway drainage and will take up to 12 weeks to complete, weather permitting.
Safety of the operatives and road users alike will be managed by barriers and temporary traffic management in place along the A146 Loddon Bypass throughout the works.
Additionally, from Monday 23 July, the following measures will be implemented:
Temporary road closures for up to 6 weeks on:
- C203 Mundham Road at its junction with the A146 Loddon Bypass.
- C203 George Lane, from its junction with the A146 Loddon Bypass to its junction with Willow Close.
A temporary speed limit reduction to 30mph on the A146 Loddon Bypass.
The County Council thanks people for their patience while this essential highway maintenance work is carried out.
The combined work, which is expected to cost £216,000, will be carried out by Norfolk County Council’s Infrastructure Department and their contractors.
For further information:
James Miles, Project Technician, 0344 800 8020.
Up-to-date information about roadworks in Norfolk is available on the County Council website at www.norfolk.gov.uk/roadworks
If you need this report in large print, audio, Braille, alternative format or in a different language please contact 0344 800 8020 or textphone 0344 800 8011 and we will do our best to help.